Severstal and Air Liquide have ahead of schedule finished the capital repairs of the largest in Russia machine to produce industrial gases at the Cherepovets Iron and Steel Works.

“The capital repairs have lasted for 11 days instead of the planned 14 days. The restoration of the compressor machinery took the most part of the time”, Severstal Russian steel repair division director Sergey Dobrodey said. (Ukrainian metal)