Chelyabinsk Zinc Works has started constructing an oxygen plant with the capacity of 10 thousand cubic meters per hour.

The need to construct the plant originated from 1995, but only after the works entered the Ural Mining and Metallurgical Company could it implement the project.

The plant is expected to be commissioned in late 2019.

The old oxygen pipeline has been operating for over 40 years. Its length is 11.3 km.

Investments in the project total 1.6 billion rubles. (Ukrainian metal)

Leave a Reply