Operations on Solton-Sary mine were resumed after a seasonal halt, press service of Kyrgyzaltyn OJSC informed.

It is noted that the gold processing plant of the mine started working. Repairs, stripping works were conducted and about 4,500 tons of ore were mined during the planned shutdown.

“The second line of the gold processing plant will be launched as part of the expansion of production at Solton-Sary mine in June. This will produce additional 6 kilograms of gold. In addition, geological exploration work continues in the promising area of Altyn-Tor that was started in January 2016. Its total reserves within the open pit mine make up about 539,790 tons of ore,” Kyrgyzaltyn OJSC commented.

The company now employs 156 people. Solton-Sary mine is one of the production branches of Kyrgyzaltyn OJSC. It is located 355 kilometers from Bishkek in Naryn region, on the northern slope of Kapka-Tash ridge at an altitude of 3,500-3,600 meters above the sea level. (24.kg/Ukrainian metal)