Russia: Metalloinvest develops rolled steel production capabilities at OEMK

Metalloinvest has commissioned a new reduction and calibration section for Rolling Mill 350’s mid-size production line at Rolling Unit No. 2 at OEMK. Investment in the project totaled more than 600 million rubles. The modernization will enable the company to increase production of high-quality rolled steel by 67,000 tons per year. The new reduction and…

Ukraine: UGOK to modernize processing factories

Yuzhniy Mining and Processing Works has repaired the technological section No. 13 of its ore-processing factory No. 2. Investments in modernization totaled 400 million UAH. All the technological sections at its 2 factories UGOK will modernize until 2022. The work started last autumn. This year it is planned to spend some 2.5 billion UAH on…