In mid-August ZEMZ received a batch of Bosio heating furnaces. Now the new batch of furnaces is being assembled in the export site of the rolling shop No. 3.

The first 5 furnaces will be assembled and commissioned in January 2018.

The company started assembly on November 7. The foundations for all the 5 furnaces are ready. To prepare each specialists poured some 28 cubic meters of concrete. (Ukrainian metal)

Leave a Reply