Construction of the gold-extracting factory is drawing to an end in Akmola region.

“The work is 87% complete. The main premises machinery is being assembled, and the substation is being constructed”, the city of Stepnogorsk mayor’s office reported.

The cost of the project is 11774 million tenge. The capacity of the factory will be 1.1 tons of Dore alloy per year, or some 14 billion tenge. (Ukrainian metal)