Russia: Olkon buys second EKG-15 excavator

Olkon has commissioned its second EKG-15 excavator. The first machine has been operating at the Komsomolsky quarry since late June. The second will be operating at the Kirovogorsky quarry. It took the company 2 months to assemble the excavator. In early 2020 Olkon will put another EKG-12 excavator into operation at the Central quarry. (Ukrainian…

Russia: Almalyk to modernize crushing complex No. 2

Almalyk Mining and Processing Works intends to modernize its copper-processing factory. In particular, the company will replace two outdated GIST-72 screens before medium crushing with 3 new SHR-24-10.5×2.3 screens, as well as 9 GIST-71 screens before fine screening with the same number of upgraded SMR-25-12.4×2.9 screens. Moreover, two new highly efficient fine crushers will be…