Despite difficulties following the accident at pipelines, the ArcelorMittal Temirtau blast furnace shop employees were able to timely finish the scheduled repair of the blast furnace No. 3.

The previous repair was carried out in November 2017.

Following the present repair the pig iron output will reach 5.6-6 thousand tons per day.

On November 21 the works carried out a blowing of the furnace.

The medium capacity of the blast furnace will be reached in 3 weeks, and the full capacity – in a month. (Ukrainian metal)