Zaporizhstal has carried out the capital repairs of its blast furnace No. 5.

According to the company statement, the financing of the overhaul was over 200 million UAH.

The repairs lasted for 36 days.

The total weight of the metal structures assembled during the repairs exceeded 1 thousand tons, and of the refractory materials – some 1 thousand tons. (Ukrainian metal)