The Sredneuralsk Copper Works, a part of UMMC, has assembled a centrifugal casting machine and two induction melting furnaces with the capacity of 1 ton each at its non-ferrous castings site.

The size of the site, which is situated in the repairs premises, is 400 square meters.

The company has also purchased two casting ladles weighing 2 tons, a sand mullor and other machinery.

SUMZ will invest a total of 57 million rubles into the modernization of the non-ferrous casting site, including 32 million rubles into the purchase of the new equipment. All the work will be performed by the end of Q2. (Ukrainian metal)