Electrocable Colchugino Works has modernized a site to test communication wire and control cables.

Investments in the project totaled 7 million rubles.

During the station reconstruction on the area of 168 square meters two separate zones have been organized. One houses the existing machinery, while the other – a new machine to test cables with high alternating voltage.

The modernization has been carried out over 3 weeks. More than 1 km of power cable was used to replace electricity network.

Daily some 50 coils of cables are tested in the shop No. 4. (Ukrainian metal)