EPM-Novocherkassk Electrode Works has started implementing an investment project to construct a Riedhammer primary roasting ring kiln.

The kiln will be constructed in the roasting shop to replace the decommissioned machinery.

The delivery of the new machinery is scheduled for H1 2019. The commissioning is scheduled for Q4 2019.

Investments in the project total 1.5 billion rubles. (Ukrainian metal)