The Uralelectromed subsidiary (Manufacture of polymetals) has commissioned the shaft furnace No. 2 after capital repairs.

The cost of repair was 47 million rubles.

It took repairmen 26 days to completely disassemble the machine with the height of 15 meters and then assemble it again. Preparation for the work started a year before the furnace was shut down.

The repairmen assembled over 100 tons of metal structures and used over 150 tons of refractory materials. (Ukrainian metal)