On March 22 the arc furnace No. 1 was put into operation.

Now the steel manufacture of Belarus Iron and Steel Works operates in normal mode with 3 furnaces.

On March 12 repairs at the arc furnace No. 3 were completed. The repairmen were able to finish the work 3 days earlier.

On March 17 the arc furnace No. 2 and the continuous casting machine No. 1 were put into operation.

Early on March 20 the continuous casting machine No. 2 started operating, and now the arc furnace No. 1.

The company is still working to restore operation after a major fire on March 5. (Ukrainian metal)