A new mini-power plant has been put into operation at the Uralelectromed enterprise – Proizvodstvo Splavov Tsvetnykh Metallov.
Its capacity is 2.4 MW of electricity or 9.2 Gcal-h of hearing energy.
The size of the premises is 450 square meters.
Commissioning took several months. At first, by the start of the heating season, a boiler room was put into operation. Then generation units were commissioned. In early January the two systems were united into one, and the mini-PP started operating in normal mode. (Ukrainian metal)