This year the Mine named after Matrosov, which develops Natalkinskoye gold-ore deposits in Kolyma, intends to mine 5 tons of gold.

Since the beginning of the year the mine has already yielded 260 kg.

To meet the target, the enterprise will have to process 9 million tons of ore and 15 million tons of rock.

The first stage of Natalkinsky GOK commissioning was in September 2017. Last year the mine processed 3 million tons of ore and 8 million tons of rock. The full capacity will be reached by late 2018. After that the annual output will be 12 tons of gold. (Ukrainian metal)

Leave a Reply