Lisichanskugol has ordered the Komsomolskaya Central Processing Factory the services of coal processing valued at 24.75 million UAH.
According to the contract Lisichanskugol will be sending to the factory the DG-grade coal with the ash content of 43-51%, sulfur of 2.9-3.5%, moisture of 11.5-13.9% and the volatile matter of 42.3%.
The coal concentrate after processing should have the ash content of not more than 28%.
The cost of processing is 99 UAH per ton.
The price of the contract is 1% below the expected cost.
After this agreement the Komsomolskaya Factory was renamed Mirnogradskaya Central Processing Factory. (Ukrainian metal)