Karelsky Okatysh has assembled new equipment at its fine crushing site – the second advanced crusher.
The replacement of the first two crushers is the beginning of the large project of the whole ore crushing network modernization. The goal of the project is to improve the quality of pellets and increase the output volumes.
One of the advantages of the new crusher is that its parameters can be changed during its operation. So far the second crusher has been 90% assembled.
“The site project presupposed the procession of 24 million tons of ore per year, now we have processed 33 million tons”, said the project manager Anatoly Nozdryakov. “In future we plan to replace six more crushers”. (Ukrainian metal)