Metalloinvest is carrying out a large-scale project to modernize the Ural Steel cogeneration plant.

The company plans to improve its energy efficiency by decreasing energy resources consumption, air pollution and maintenance costs.

Under the project Ural Steel is constructing a complex with two boilers of medium pressure with the capacity of 220 tons of steam per hour each.

Commissioning is scheduled for H2 2020.

In April the company replaced electric equipment at the connection transformer No. 2. The same will be done with the transformer No. 3.

In future the company plans to gradually replace all the five high-pressure boilers, turbo generators and air compressors. (Ukrainian metal)

Leave a Reply