ArcelorMittal Kriviy Rih has finished the scheduled repair of the blast furnace No. 7.
According to the company statement, as a result the pig iron output increased to 16 thousand tons per day, and will have further increased to 17 thousand tons by mid-October.
Investments in the repair totaled 240 million UAH.
The repair started in late May and has lasted for 110 days. (Ukrainian metal)