Rusolovo intends by the end of 2022 to have constructed and commissioned the mining and processing works at the Pravourminskoye tin ore deposits.

Investments will total 9.7 billion rubles. Construction of the GOK itself will cost 6.7 billion rubles.

The company will also have to construct a road from the site to the settlement of Suluk. It will cost 3 billion rubles.

The construction of the road will start in 2019 and should be complete by 2021 end.

The construction of the GOK will start in 2020. (Ukrainian metal)