Izhorsky Pipe Works has carried out capital repairs of its main machinery, having completed the spring repair campaign.

“The repairmen only had three days. But despite the short terms, they coped with the ambitious task. The capital repair will provide for the stable operation of the machinery and will extend its lifetime”, ITZ CEO Dmitry Pokrovsky said.

The Severstal spring campaign also included the repair of the Cherepovets Iron and Steel Works mill-5000. It lasted for 7 days. (Ukrainian metal)

Leave a Reply