The Stoylensky Mining and Processing Works has replaced an old crushing mill with a new KKD1500/180 machine.
The capacity of the new mill is 1.9 thousand cubic meters per hour.
The machine was manufactured by Uralmashzavod.
The record-short time assembly allowed the company to keep output on the planned level.
At present the new crushing machine is processing the ferruginous quartzite. Next week the mill will reach its project capacity.
The previous crushing machine has been in operation since 1983. (Ukrainian metal)