Zaporizhstal plans to finish the construction of the gas-purifying complex for its sintering machine No. 6 in October.

“We have been constructing gas-purifiers for the past two years. By the end of October the construction of the sixth sintering machine gas-purifier will have been completed and the whole sintering shop gas-purifying complex will have been put into operation, resulting in the decrease of emissions”, said the company CEO Rostislav Shurma.

The investments into new gas-purifiers at sintering machines No. 3-6 amount to 630 million UAH.

In 2015 Zaporizhstal received 1.8 billion UAH of net profits, up by 61% YoY, or by 684.3 million UAH. (Ukrainian metal)