Russia: Kopy Goldfields reviewing two ways to develop Krasnoye deposit

Kopy Goldfield AB (Sweden) has two ways to develop the Krasnoye deposit in Irkutsk region.

The first is the combined development. At first a processing factory with the capacity of 1 million tons of ore per year and an open quarry at the Krasniy site will be constructed. After that a mine will be constructed. Capital expenses are estimated at $149 million.

The second way is to develop the deposit via an open-pit. A processing factory with a capacity of 3 million tons per year will have to be constructed. Investments will amount to $250 million.

In 2018, Kopy Goldfield increased Krasnoye resources by 32%, to 1.832 million ounces of gold. (Ukrainian metal)