Dneprovsky Iron and Steel Combine will carry out capital repairs of its converter No. 1

The waste-heat boiler has almost been disassembled, and the subcontractors have started disassembling a coffer.

At the same time a new waste-heat boiler is being assembled. All the technical documentation has been received.

Some 200 employees work at the site each day. The expected term of the capital repair is 55 days. (Ukrainian metal)