Zlatoust Electrometallurgical Works has finished assembly of railroad to transport the floor-type loading machine at the thermal annealing furnaces site being constructed in the rolling shop No. 3.

The foundation for the rails with the length of 48 meters each has been completed.

At present the floor-type loading machine is being assembled.

Bosio annealing furnaces arrived at the ZEMZ site in mid-August 2017.

The commissioning of the site is scheduled for June.

The capacity of each furnace is 900 tons per month on average. (Ukrainian metal)