Within the reconstruction of its pelletization factory the Central Mining and Processing Works has completed the first stage of the factory modernization.

The company has put the Eirich batch-blending machine into operation. The new equipment costs 15 million UAH. The total investments into the project will reach 61 million UAH.

The second stage is the replacement of the pellets rolling stacker with the modern screen. This part of the project will be implemented in early 2017. (Ukrainian metal)