By January 1, 2016 DTEK has completed its repair program worth 1.5 billion UAH.

Out of the 66 planned overhauls the holding has carried out 65 (56 current repairs, 5 medium repairs and 4 capital repairs).

Only power unit #4 of Zuev Thermal Power Station was left without the scheduled medium repairs.

As of January 11, DTEK thermal power stations stocked 1.55 million tons of coal, up by 77% YoY. (Ukrainian metal)