Until December 20 Russkiy Chrome 1915 intends to carry out a scheduled repair of the drainage system around its sludge collector No. 1.
The pump station No. 3 has already been shut down in order for the electric pump to be replaced.
The modernization of the drainage system is a preparatory stage to assemble new GEA purifying equipment at the neutralization station. 2 unique decanters valued at over 2 million euros will help the company decrease waste content in pool-collectors and remove liquid wastes.
Since Russkiy Chrome 1915 joined MidUral Group, some 3.5 billion rubles have been invested in the manufacture modernization. Emissions to the Chusovaya River decreased 6-fold as a result. (Ukrainian metal)