Sredneuralsky Copper-Smelting Works has started the scheduled repair of the Vanyukov furnace No. 1.
The company intends to invest some 238 million rubles in the repair.
The furnace commissioning is scheduled for June 8.
The Vanyukov furnace No. 1 was put into operation in 1994, and No. 2 in 2009. (Ukrainian metal)