Ukraine: DMK getting ready to put converter and CCM into operation

Dneprovsky Iron and Steel Combine is preparing its converter shop for operation.

In particular the work is being carried out at the converter No. 2 and the continuous casting machine No. 1. The steel- and pig iron pouring ladles have been heated, and the first pig iron will be poured on July 27.

The rolling shop is preparing the machinery of the 400/200 mill.

Blast furnaces No. 1M and No. 9 were blown on July 23. (Ukrainian metal)