The drainage system of the Ingulets Mining and Processing Works quarry has been modernized.
In order to maintain the drainage capacities, tubes were relocated.
Investments in the project exceeded 14 million UAH.
Two branches of tubes of 975 meters each have been laid.
One of the branches has been commissioned,
The modernization of the system improved pumps’ capacity by 9%. (Ukrainian metal)