Mariupol Ilyich Iron and Steel Works has finished constructing dust-exhaust systems for the blast-furnace manufacture.
The cost of the project was over $31 million.
The construction began in August 2019.
Soon bag filters will be installed at all blast furnaces. (Ukrainian metal)