Karelsky Okatysh has shut down its manufacture for 60 hours to carry out scheduled repairs.
Concentrate and pellets manufacture saw the most of repairs, as they could have been carried out only when the plant was shut down, and the water used in the production was switched off.
The company has replaced a transformer substation. Previous machinery has been working for over 35 years. 3 more substations have also been repaired.
The next scheduled shut down will take place in a year. (Ukrainian metal)