VSMPO is reconstructing vacuum arc furnaces Nos. 17 and 18 in the shop No. 31.
After modernization they will be able to produce ingots with the weight of 4 tons as opposed to 2 tons previously.
The work started in November 2018.
In 13 months the furnaces have to yield the first ingots. (Ukrainian metal)