PPGHO named after Slavsky has started constructing a foundation pit for the mine water treatment plant.
By the end of the year contractors have to make foundations of the auxiliary buildings and structures.
The contracts for the delivery of the main machinery (pumps, transformers, conditioners, etc.) have already been concluded.
The facility is to be commissioned in late 2019.
A new road to the mine No. 6 will be put into operation in October ahead of schedule.
The readiness of the main substation is 95%.
The first stage of the uranium mine No. 6 has to be commissioned in 2023. (Ukrainian metal)