The 23-ton hammer has resumed operation at the shop No. 3 of VSMPO-Avisma after capital repairs.
In a month the main elements of the structure – steel pillars – have been replaced.
On September 21 the commissioning of the hammer began. In a day, after all the minor malfunctions have been corrected, the hammer was put into operation. (Ukrainian metal)