ArcelorMittal Kriviy Rih has said that in September this it had managed to stabilize its production process and to solve problems regarding the operation of its sinter plant.

Mr. Rinat Starkov, CEO of ArcelorMittal Kriviy Rih, said “The main steps to restore the operation of equipment have been implemented, and the process must be fully completed in the first two weeks of October. In general, the enterprise worked well in September, but in October we expect to see the main impact of the measures undertaken to stabilize the production process.”

Products

August 2010, t

September 2010, t

MoM, %

September 2009, t

YoY, %

Pig iron

404,000

447,700

10.8

218,800

104.6

Steel

462,400

510,800

10.5

251,400

103.2

Rolled steel products

476,200

452,000

-5.1

264,800

70.7

Products

January-September 2009, t

January-September 2010, t

Change, %

Pig iron

3,083,900

3,934,700

27.6

Steel

3,508,100

4,526,600

29.0

Rolled steel products

3,226,400

3,981,600

23.4

(SteelOrbis)