Mariupol Ilyich Iron and Steel Works has started assembling metal structures of the roof at the continuous casting machine No. 4 building.

“Since the start of the construction over 1.5 thousand tons of metal structure columns and beams have been assembled”, the company CEO Yuri Zinchenko wrote on his Facebook page.

The works has also completed the foundation for some of the main machinery. (Ukrainian metal)