Zaporizhstal has completed the disassembly at the blast furnace No. 3 reconstruction site. The total weight of the structures disassembled exceeded 12 thousand tons.

“In 60 days we have completely disassembled the structures of the old furnace and freed the site to start construction”, Zaporizhstal CEO Rostislav Shurma said.

Investments in the project amounted to 1.5 billion UAH. (Ukrainian metal)

Leave a Reply